Projects
SBC# |
Project Name | Description | Project Cost | Funding Source | Approved Date | Approver |
369/005-05-2023 | Millennium Center Chiller Replacement | This project will install a chiller(s) and all related components/work to serve the building's cooling needs and all related work. | $1,500,000 | Plant Funds (Non-Aux) | July 1, 2023 | COO |
369/005-01-2024 | Bosque Plaza | This project will connect the site of the new Academic Classroom (SBC# 369-005-05-2021) building with the current pedestrian way known as the "Commons" (Boulevard Commons SBC# 369/005-08-2021) creating a plaza that highlights trees surrounded by hardscape. | $2,100,000 | Plant Funds (Non-Aux) | March14, 2024 |
COO |
369/005-02-2024 | Brinkley Center Renovation | This renovation project will be approached in two phases. This project will create collaboration and office space within the Brinkley Center. This work will consolidate faculty into this primary building of instruction space for the Department of Computing. The collaboration space will better facilitate opportunities for students and faculty to interact. This renovation may include ceilings, finishes, plumbing, HVAC, electrical, lighting, sprinkler systems, and other related work as needed. |
$2,000,000 (total)$1,000,000 (this request) |
Plant Funds (Non-Aux) | April 11, 2024 | COO |
369/005-03-2024 | Greenhouse Installations | Dismantle of existing greenhouse and replace with two small greenhouses. Installation of two new greenhouses on main campus. Work to include sitework, concrete work, furnishing and installation of two new greenhouses, and all associated work. |
$480,000 |
Plant Funds (Non-Aux) | April 11, 2024 | COO |
369/005-xx-2024 | ETSU Sodexo Food Service Improvements (23-24) | Convert the "Subway" in ETSU Parking Garage to a Sodexo branded salad and sandwich shop. Work also includes conversion of the ETSU "Treehouse" sandwich shop into a convenience store. |
$990,000 |
Gift-In-Place (Contract) | TBD | COO |